GenCos fail to generate 3,347.5 megawatts due to gas shortage

Electricity Generation Companies (GenCos) comprising gas-fired and hydro- stations said that they could not generate 3,347.5 megawatts of electricity on Wednesday due to unavailability of gas.

serap-DailyTime

This information was made known in a daily energy report by the advisory power team in the office of the vice presidentin Abuja on Thursday.

The report also noted that 220 megawatts of electricity was not generated due to the unavailability of transmission infrastructure during the period.

Similarly, it said that 400.4 megawatts was not generated due to high frequency resulting from unavailability of distribution infrastructure.

The report however, said that the GenCos released an average of 4,140 megawatts/hour of electricity into the national grid on Wednesday.

READ ALSO: Ogun declares zero tolerance for female genital mutilation

It said that the electricity sent out by the GenCos was down by 95.89.13 megawatts from the 4,286 released on Tuesday.

The report revealed that the power sector lost an estimated N1.9 billion on Wednesday due to insufficient gas supply, distribution and transmission infrastructure.

On sector reform and activities, it said that the dominant constraint for Wednesday was unavailability of gas. The report said that the peak generation attained on Thursday was 4,502.5 megawatts.